-
On Mars:
Exploration of the Red Planet. 1958-1978
-
-
-
- VIKING MISSION DEFINITION NO.
2
-
-
-
- [174] The Viking project definition
document was another element in Jim Martin's attempt to create a
viable Mars exploration activity. Revised several times, the
document gave project participants a general description of the
Viking missions. By August 1969, the document had been updated
five times, the latest edition being called "Viking Project
Mission Definition No. 2." This 21-page paper was prepared by a
group working under A. Thomas Young, the science integration
manager, at Langley. Three men had to approve it before it was
released 11 August 1969-Gerald Soffen, project scientist; Israel
Taback, engineering manager and deputy project manager; and Jim
Martin. "Viking Project Definition No. 2" contained a more nearly
complete description of the entry and lander science experiments
that would be included in the lander capsule and the lander. These
experiments had been defined through the work of the Science
Steering Group, chaired by Jerry Soffen. 34
-
- In August 1969, there were eight science
instrument teams: orbiter imaging, biology, molecular analysis,
meteorology, entry science, radio science, seismology, and
ultraviolet photometry. Each of the lander experiments was further
described in the "Viking Lander Science Instrument Teams Report,"
which served as an important reference on the state of instrument
design, the scientific rationale for the experiments, and for
studies that might lead to ways of increasing the scientific
capability of the instruments. The instrument team report and
"Viking Project Definition [175] No. 2" provided the basis for
spacecraft design negotiations with Martin Marietta and the
starting point for "early Project activity including the
initiation of mission, spacecraft and operations design."
35, Although the mission definition was geared toward
getting lander hardware design and fabrication started, it also
had significant impact on the orbiter design team.
-
- Henry Norris told his people at a 27
August staff meeting that the mission definition had been
distributed to all the JPL division representatives. Since this
was a controlling document for the project, Norris's team would
have to reconcile its "resources," or budget, with its baseline
definition of the orbiter. Some differences existed, for example,
between the communications requirements as stated in the
definition document and as pursued by the JPL engineers. "The main
requirement causing a significant impact is that of the orbiter
having the capability to communicate with either lander." Norris
asked division representatives "to flag any other areas of
disagreement," 36
-
- As Norris and his staff worked on the
orbiter design, the mission definition continued to evolve. A
number 3 edition would be ready in January 1970 after the final
selection of science investigators by NASA Headquarters in
December. The number 4 version would be prepared in the early
spring of 1971, reflecting any changes that came from the Viking
project critical design review. Finally, some time after June
1972, "Viking Project Mission Definition No. 5" would be issued to
reflect lessons learned from the Mariner 71 mission. From October
1969 onward, the mission definition documents would be used in
conjunction with "project specification" documents to monitor the
effort. 37 Meanwhile, the science results from Mariner 6 and
7
had to be incorporated into the Viking plans.
-
-
-
-